The Hynes Convention Center remains active while crews complete substantial renovations, signaling strong continued interest even before the building is back to full strength.
There’s substantial variance in how busy the center will be, with some months booking over 20 days of events and others none at all. The work itself seems to be going well, with the Massachusetts Convention Center Authority (MCCA) reporting no substantial hiccups and estimated that the repairs will be done within five years.
It’s
a substantial turn of fortune for the Hynes, which was on the state’s
chopping block as recently as 2022. The sale wasn’t finalized under the
administration of Charlie Baker, however, and Governor Maura Healy’s
MCCA opted instead to undertake the building’s long-deferred
maintenance.
The Hynes
needs around $300 million in repairs, with a 2015 report detailing up
to $500 million in excessive occupancy on the third floor, widespread
accessibility issues, structural problems, plumbing problems, the need
for new fire systems and issues with internal walls.
“Currently,
work is underway to replace the fire pump, which is integral to the
function of the sprinkler system, as well as replacement of the air
handling units and the main electrical switchboards responsible for
delivering power throughout the facility,” said an MCCA spokesperson.
Officials
first claimed in February they could juggle construction with
continuing to hold events, and they seem to have pulled off that
balancing act. While some months are less active than others, the
busiest have events scheduled more days than not.
On
average the center has 9 days booked for events per month. The busiest
time will be in the spring, with May topping the list at 21 days of
events. That will be immediately followed by a summer largely devoid of
programming, with June only having one day booked and August having none
at all.
“These
projects are critical to the occupancy of the building but have been
strategically scheduled to best accommodate current clients while
addressing the work in a timely manner,” said the MCCA.
“To
accommodate the strong demand for future business at the Hynes, our
capital projects team is working with our sales and event planning
teams, as well as our partners in the Back Bay to allow for future
bookings at the Hynes for any open windows as we work on and continue to
invest in the Hynes.”
The
center is remaining active during maintenance, but it will still be
years until it’s back to full capacity. Current MCCA projections have
the building back up to code in around five years, a bit more than
initial optimistic estimates of two to three years.
“While
some projects, such as the electrical switch board replacements, have
been phased strategically to ensure our clients can occupy the building,
windows of availability at the Hynes will vary year to year based on
the nature of the projects being carried out. We are also now booking
contracts at the Hynes for all time periods starting in the second
quarter of 2029,” said the MCCA.